Roadmap
-
Milestone: Concept demo with some statewide plan data
17 months late (06/23/08)
Have a conceptual demo running that include real MN statewide plan data, see the green path on this diagram.
2008-4-22: follow path without GIS / map component initially
Rescheduled from Mar 09 2008 to Jun 23 2008
-
Milestone: Data schema defined
16 months late (07/18/08)
Schema for various data components (input filters etc.), defined in DocDesign, sufficiently defined to allow development based on them.
Rescheduled from Apr 10 2008 to Jul 18 2008
-
Rescheduled from Apr 23 2008 to Jul 28 2008
-
CorePresent? working for at least one output type.
Rescheduled from Jun 06 2008 to Sep 01 2008
-
Milestone: Advance DocDesign to working draft
14 months late (09/19/08)
DocDesign, based on the original long version proposal, needs to be expanded to the point where development can use it as a reference. DocDesign will however continue to evolve.
This was originally an early priority, but now seems better left until more initial development work is done, guided by the examples in DocUserGuide.
Rescheduled from Jul 01 2008 to Sep 19 2008
-
Milestone: User and session management implemented
13 months late (10/04/08)
EnvSessions? and EnvUsers? components
Rescheduled from Jul 20 2008 to Oct 04 2008
-
Milestone: Output presentation - mapping
12 months late (11/09/08)
CorePresent? includes mapping output functionality
Rescheduled from Sep 04 2008 to Nov 09 2008
-
Milestone: All CoreProcess methods functional
10 months late (01/16/09)
All data transformations CoreProcess? supports should be implemented
Rescheduled from Nov 30 2008 to Jan 16 2009
-
Milestone: All output formats functional
8 months late (03/27/09)
All the output formats defined for CorePresent? completed
Rescheduled from Feb 28 2009 to Mar 27 2009
-
Milestone: Final documentation release
6 months late (05/08/09)
Documentation will be developed and available throughout the project's lifecycle. It should be complete and final by this date.
Rescheduled from Apr 24 2009 to May 08 2009
-
Milestone: "Complete" set of import filters for MN natural resource data sets
4 months late (06/30/09)
Import filters, i.e. user access files, for MN natural resource data sets will be accumulated throughout the project's life, but the set as available at this date will be considered the final required release from th project.
Rescheduled from Jun 30 2009 to Jun 30 2009